Shenhua Dynamic Compaction Project
Construction of the full‑plant dynamic compaction works for the Shenhua Ningmei 4-million‑ton‑per‑year coal indirect liquefaction project (Section II) is being undertaken by the client, Shenhua Ningxia Coal Industry Group Co., Ltd. The project site is located in the Ningdong Coal Chemical Base (Area B6), Ningxia Hui Autonomous Region. The total area of ground improvement amounts to approximately 386,900 square meters, with dynamic compaction energy levels of 4,000 kN·m, 6,000 kN·m, 8,000 kN·m, 10,000 kN·m, and 12,000 kN·m. The overall construction period is 60 days.